Project on Hold; will resume in Spring 2021

Greetings and welcome to your project blog for the upcoming painting project at Water’s Edge Manor in Hugo. We are thrilled to be onsite with you!


Thursday, October 22nd: Greetings! 

Well, the snow came fast and furious. We are going to put your project on HOLD and resume in the spring with the  remainder of the staining to 5 decks.

Thanks so much for your continued patience. We’ve learned that Mother Nature has her own agenda and we have to work around the elements — rain putting the biggest delay on your project the week of October 12th.

We hope you all have a great rest of the year and we’ll see you in the spring. Thank you!

Friday, October 16th: Hello and Happy Friday!

We’ll be back onsite on Sunday to finish up the remaining ~ 10 decks to stain. Thanks so much and have a great weekend!

Thursday, October 15th: Good morning! 

We are back at it! 

We thank you all so much for your patience as we are doing our best to complete this staining project quickly and have run into a few stops because of weather. 

The crew is working starting at Building 32 today. 

Prepping and sanding the deck boards.

Staining the deck skirts.

Tuesday, October 13th: Greetings! 

We will resume our prep and staining tomorrow at Water’s Edge Manor. We want to be sure the decks are fully dried with the rain the other day and then some cooler weather. Thank you!

Friday, October 9th: Good afternoon! 

We are starting off at Building 27 with stain today. Reminder to please wait 24 hours before returning items to your deck. Thanks and have a great weekend! 

Thursday, October 8th: Good morning! 

The crew is starting off at Building 14 today with staining. They’ll be back onsite on Friday and Saturday to continue staining along the route. Thanks! 

Staining along the deck kickplate.

Moving right along in Hugo!

Refreshing the deck posts.

Wednesday, October 7th: Good afternoon! 

It’s a beautiful day to be onsite and staining decks at Water’s Edge Manor Homes. The crew is starting off at Building 11 marked on the map above. Thanks! 

Sanding the posts.

Prep work and taping off the edges.

Staining the posts.

Tuesday, October 6th: Good morning! 

The crew is onsite and continuing to stain the included decking today. We’ll soon post how far along the route they stained yesterday. Thanks!

Staining the deck boards.

Sprucing up the deck skirts.

Wednesday, September 30th: Greetings! 

The crew is washing a few decks that were skipped/missed today. They will return on Monday, 10/5 to begin staining starting at the beginning of the route. Thank you!

Monday, September 28th: Good morning! 

With yesterday’s rain we are going to hold off on starting to stain the decking today at Gables Manor. And depending on this afternoon’s weather, we’ll either get started tomorrow or Wednesday. Thanks!

Thursday, September 24th: Greetings! 

The crew has made it through the rest of the washing of your decking. They’ll return on Monday to begin staining – back at the beginning of the route. 

Thanks and have a great weekend!

Wednesday, September 23rd: Good afternoon! 

The crew is onsite and continuing to wash the included decking for this year’s project. They’ll be working through tomorrow to get them all washed. They started off at Building 30 today so they’re completing about 15/day. Thanks!

Washing and readying the decks for staining.

Spraying the deck skirts.

Continuing to wash the deck floors at Water’s Edge Manor.

Tuesday, September 22nd: Good morning! 

The crew washing ~ 15 of the decks yesterday and are project to finish the pressure washing by the end of the day tomorrow. But with 50 decks to clean and wash this may spill into Thursday as well.

They’ll begin staining on Thursday, 9/24 back at the beginning of the route on as long as we can keep this dry weather. 

Washing the deck floors.

Monday, September 21st: Good afternoon! 

And they’re off! 

The crew is getting started with the pressure washing portion of the project today. Starting at Building 1 and making their way along the route washing the included decking. 

We’ll share how many decks were washed today and try to project which day your deck will be washed. Thank you for your patience as we get underway with your large decking project. 

And they’re off!

Friday, September 18th: Good morning! 

Welcome to your project blog for the upcoming decking project at Water’s Edge Manor. We are looking forward to being onsite with you! 

Our will be getting started on Monday, 9/21 with pressure washing the included decking areas starting at the beginning of the route. We are anticipating to wash about 10-15 decks/day and will be finished with the washing by Friday, 9/25. We’ll be pressure washing in advance of the staining of deck skirts, posts, and wood deck floors. 

Thank you in advance for removing the items from your decking for unobstructed access while washing and then staining. We are hopeful to start the staining at Building 1 on Thursday, 9/24, weather permitting starting again at the beginning of the route.  We know this project will impact your daily routine and we will do our best to complete the project promptly so everyone can enjoy the remained of the summer/fall and return contents to their decks as soon as they’re able.

You can continue to follow the project progress here on the blog as we’ll post frequent updates, share photos, and let you know of delays should they come up. 

Have a great weekend and we’ll see you on Monday!


Dana Clark

Project Manager
Ph: 763-559-5296
Email

Hirsh Logo
Sherwin Williams Logo
Cabot Stain Logo
PPG Logo
Sikkens Logo
Benjamin Moore Logo

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423