Greeting and welcome to the project blog for the upcoming painting project at Ridgewood. We are looking forward to getting started!

BUILDINGS PRESSURE WASHING DATE STAINING START DATE
1 Thursday, July 9th Wednesday, July 15th 
2 Friday, July 10th Thursday, July 16th
3 Wednesday, July 8th Monday, July 13th
4 Monday, July 13th Friday, July 17th
5 Tuesday, July 14th Monday, July 20th
6 Wednesday, July 15th Wednesday, July 22nd
7 Monday, July 20th Thursday, July 23rd
8 Tuesday, July 21st Friday, July 24th
9 Wednesday, July 22nd Monday, July 27th
10 Thursday, July 23rd Tuesday, July 28th
11 Friday, July 24th Wednesday, July 29th
12 Monday, July 27th Thursday, July 30th
13 Tuesday, July 28th Friday, July 31st
14 Wednesday, July 29th Monday, August 3rd
15 Thursday, July 30th Tuesday, August 4th
16 Friday, July 31st  Wednesday, August 5th

Thursday, August 6th: Good afternoon! 

The crew finished up staining Building 16 yesterday and will be wrapping up the painting today as well. We’ll then come through to take care of any areas needing touch ups in the next few days. Thanks!

Tuesday, August 4th: Good morning! 

The crew is right on schedule and prepping and staining your decking at Building 15 today. They’ll be completed the staining at Building 16 tomorrow and then wrapping up with the painting on Thursday as well. 

Prepping and covering before staining the stairs.

Painting along the stair skirt.

Staining your deck boards.

Slow and steady to apply the stain.

Thursday, July 30th: Good afternoon! 

We are right on track – washing at Building 15 and also staining at Building 12. 

Staining your entry steps at Building 12.

Gliding that stain on the deck boards.

Building 15 gets all washed and ready for stain.

Wednesday, July 29th: Good morning residents of Ridgewood!

We will be posting notices for washing and staining the remaining 3 buildings today and we will be resuming our washing and staining schedule as is posted above. We apologize for the miscommunication. The crew will continue to stain the decking on Building 11 today as well.

Tuesday, July 28th: Greetings! 

Back at it! We are washing Building 13 today and also staining Building 10. 

Painting the deck skirts.

Prepping and covering before applying the stain.

Staining at Building 10.

Monday, July 27th: Good afternoon! 

We hope you all had a great weekend! 

The crew has returned and is resuming their pressure washing at Building 12 and staining at Building 9. Thank you! 

Staining deck boards at Building 9.

Staining down the steps.

Taping off the outer edge of the deck boards.

Friday, July 24th: Greetings!

Happy Friday! It’s going to be a HOT one folks – stay cool out there 😎

We are right on schedule with washing Building 11 and staining at Building 8 today. 

Have a great weekend!

Thursday, July 23rd: Good morning! 

The crew is onsite today and they are washing at Building 10 and then staining at Building 7. Thank you!

Staining at Building 7 today.

Moving along to Building 10 with washing.

Tuesday, July 21st: Good morning! 

The crew will not be staining at Building 6 today because of the rain. They will still pressure washing Building 8 though. We’ll soon update the staining schedule to reflect today’s weather delay. Thanks!

Monday, July 20th: Good afternoon! 

The crew is washing Building 7 today and also staining at Building 5. The schedule above reflects our tentative finishing schedule for washing and then staining. 

You may return items to your decking 24 hours after staining – thanks! 

Spraying down the decking.

Building 7 is getting washed and ready for staining.

Thursday, July 16th: Good morning! 

The crew is staining at Building 2 today. We’ll be posting more notices to wash more of your buildings starting on Monday, 7/20 with Building 7 and will wash one each day next week. We’ll continue to stain one building each day and the crew will begin to paint the deck skirts as well — starting at Building 1. 

Staining the stairs.

Before picture of the deck.

Finished deck!

Wednesday, July 15th: Good afternoon!

The crew is washing Building 6 and staining at Building 1 today.

Staining the stairs.

Staining Building 1.

Monday, July 13th: Good morning! 

The crew is continuing to pressure wash the decking – completing Building 4 today. They have also started to stain the decking on Building 1. We’ll post later how many of the decking areas they get through for today. Thanks!

Pressure washing at building #4 today.

Stained and looking fresh!

Ready for stain.

‘Before.’

All spruced up at your entry steps.

Wednesday, July 8th: Greetings!

We are washing at Building #3 today. There was a mix up with the washing and we will be going back to Buildings #1 and #2 to rewash them starting tomorrow and Friday – see the updated schedule above. We’ll then pick back up with Building #4 on Monday, July 13th. Staining will begin at Building #1 on Tuesday, July 14th. Thanks for your patience!

Tuesday, July 7th: Good morning! 

We are back at it and washing Building #2 today. 

Spraying down the stairs.

Don’t forget the sides!

Monday, July 6th: Greetings! 

We are off  and running at Ridgewood with pressure washing of Building #1 today. We’ll continue to wash 1 building/day for the remainder of this week and we are tentatively set to begin staining on Friday, July 10th. 

Spraying the deck floors.

Washing the entry steps.

And they’re off!

Readying your decks for staining.

Tuesday, June 30th: Good afternoon! 

Welcome to your project blog! We will be getting started on Monday, July 6th with pressure washing. 

We’ll wash 1 Building/day next week so we will get through washing Buildings 1-5 by Friday. We are anticipating to begin staining decks on Building 1 starting on Friday, July 6th. We are projecting the crew will take about 1.5 days to complete the staining on each building. As you can see in the table above that is reflected in the ‘Staining Start Date’ column. The crew will wash and then stain the decks in the order shown on the route map posted above.

We’ll update the dates for washing and then staining the rest of the buildings and we finalize and know the crew’s pace for completion. Thanks! 

Monday, June 15th: Good Morning! 

Welcome to your project blog for the painting project at Ridgewood in Savage. We’ll be kicking off your project in the next week or two. We’ll soon post more information regarding start date and a tentative finishing schedule. 

You can continue to follow the project progress here on the blog as we’ll provide frequent updates on progress and scheduling, share photos, and inform you of any weather delays.

Thank you so much for having us and we are looking forward to being onsite!

 

Dana Clark

Project Manager
Ph: 763-559-5296
Email

 

Hirsh Logo
Sherwin Williams Logo
Cabot Stain Logo
PPG Logo
Sikkens Logo
Benjamin Moore Logo

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423