Greetings and welcome to your project blog for the upcoming deck railing painting and staining project at Palomino Apartments. We are thrilled to be onsite!


Thursday, June 18th: Good Morning!

The crew is finishing up the deck staining today and will return tomorrow for touch ups!

Wednesday, June 17th: Greetings!

The crew is finished! We will do a walk through soon and come back to complete touch ups in the next few days as well. 

Adding some finishing touches!

Tuesday, June 16th: Good afternoon! 

It’s a steamy one folks – stay cool & stay hydrated!

We’ll be about 2/3 complete after today and will be finishing the staining tomorrow. 

Sprucing up and staining your decks.

Ready for some stain.

Monday, June 15th: Good Morning! 

The crew has started staining your decks and will be working their way around your building. Thanks! 

Hard at work on the upper units.

Deck staining has begun!

Friday, June 12th: Hello and happy Friday! 

We will be returning on Monday, June 15th to begin staining your deck floors — starting again at the main entrance and moving clockwise around. Thanks for your patience as we got your stain match approved. 

See you on Monday!

Monday, June 8th: Greetings! 

It’s a HOT one today!

The crew will be wrapping up on the the railing painting today. We are waiting on approval for the deck stain. Stay tuned for when we’ll start staining. Thanks! 

Moving around to the rear side of the building.

Ladders up and painting railings on this hot day!

Thursday, June 4th: Good afternoon! 

The pressure washing is complete and we have 2 crew members scraping and sanding and then 2 crew members following behind priming and painting the railings. Thanks!

Covering and prep in progress.

Prepping and priming this deck stack’s railings.

Ladders onsite and we’re going up!

Wednesday, June 3rd: Greetings!

The crew had about 10 patios to finishing pressure washing today. They will then start painting the metal railings — beginning at the entry way and moving clockwise around the building, as was done for the washing. Thanks!

Tuesday, June 2nd: Good afternoon!

The crew is on the backside of the building and nearing back to the starting point. They will either finish up the washing today or tomorrow morning – thanks!

Cleaning and washing the deck floors.

Using detergent to clean off the surface.

Working on the upper units.

Monday, June 1st: Good morning! 

We are off!! The crew is onsite and pressure washing the deck stack floors starting at the Main Entry and then moving clockwise around the building front and to the back. Once washed, we’ll begin with the railings and then finish with the deck staining. 

Ladders up to wash the upper deck floors.

Washing off the deck floors.

Cleaning and readying the decks for staining.

Wednesday, May 27th: Good afternoon! 

Welcome to your project blog for the painting and staining project at Palomino Apartments. We are set to begin pressure washing the deck floors starting on Monday, June 1st. We will first be completing the pressure washing on all units. The crew will be following the route posted above — starting at the main entry and working clockwise around to the deck stacks. The washing will take about 3-4 days and then we will begin the railings and finally complete the deck floors – each moving around the route above.

For the pressure washing we kindly ask that you remove all items from your deck to allow unobstructed and complete washing. Once washed, you may return items to your deck, but away from the railings so we can paint them. You will be asked to remove contents from deck a 2nd time while we stain your deck. You will be notified of this via a 2nd notice of when the staining will be scheduled. 

This is a large project and we will be onsite for about 2-3 weeks. We will post frequent updates here on the blog regarding progress, scheduling, and any weather delays should they come up. Let us know if you have any questions – contact info is below or you can leave a comment. Thanks!

Thank you in advance for your cooperation to remove items from your deck! We will see you on Monday

 


Dana Clark

Project Manager
Ph: 763-559-5296
Email

 

Hirsh Logo
Sherwin Williams Logo
Cabot Stain Logo
PPG Logo
Sikkens Logo
Benjamin Moore Logo

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423