MN Transitions Charter School – Minneapolis

MN Transitions Charter School- Minneapolis

Project Complete

Greetings and welcome to the blog for the upcoming project at MN Transitions Charter School in Minneapolis. We are thrilled to be onsite completing work with and for you!


Monday, August 12th: Good morning!

We hope everyone had a great weekend!  The final walk through has been done and the crew completed the touch ups that were marked.  This means your project is officially completed!  It has been our pleasure to work with and for you this summer.

Thursday, August 1st: Greetings!

One of our production managers will be onsite today to do a final walk through and mark any areas in need of touch ups.  The crew will then return to complete those and the project will be officially finished!

Thursday, July 11th: Good morning!

Today our crew is onsite to continue painting walls white and yellow. We are really liking how all the accent colors are coming together. 

Giving this yellow accent wall a refresh.

Continuing to paint all the walls.

Monday, July 8th: Good afternoon!

We have been working onsite throughout the holiday and are onsite again today to continue making way on the project. 

Prepping the staircase to assure no paint gets on them while we refresh the walls.

Tuesday, July 2nd: Greetings!

The best part about an interior project is that Mother Nature doesn’t stop our crews from continuing to pave way on the project. We are excited to continue tackling this project!

Giving the doorframes a refreshing coat.

Continuing to make progress on the project.

Monday, July 1st: Good Morning!

Happy 1st of the month! We are continuing to make great progress while onsite, as more progress is made the anticipation builds to see the final product. 

Giving this green accent wall a refreshing makeover.

Continuing to make great progress throughout the building.

Wednesday, June 26th: Good afternoon!

Our crews are continuing to make way on the project! Our team is eagerly anticipating advancing further into this project and can’t wait for the final result. 

Transforming classrooms with fresh coats of paint.

Making sure every crevice of the doors get this beautiful blue.

Using a brush to get close to the ceiling to ensuring a seamless result.

Tuesday, June 25th: Greetings! 

Our onsite crews are making great progress prepping and painting their way throughout the building. We’re thrilled to continue tackling this project and breathe new life into the interior!

We use paint rollers in order to cover large areas and make sure the whole surface gets an even coat.

We go in with brushes to make certain no spots were missed and ensure a seamless result.

Monday, June 24th: Good afternoon!

The crews onsite have made great progress so far and continue to work their way around the building prepping & painting.  We are excited to tackle this project and refresh the interior!

Lots of prep work to ensure the project runs smoothly!

Nothing beats a fresh coat of paint!

Thursday, June 20th: Greetings!

Welcome to your project blog for the upcoming project at Minnesota Transitions Charter School!

This project blog will be used as a communication tool to relay pertinent project information regarding start dates, photos of progress, and updates to the finishing schedule. We are excited to be a part of your renovation project.

This project includes repairs and painting of almost the entire interior of the school! In order for painting to take place, our crew was onsite today making sure everything was being prepped. 

As we kick things off with your project today with some of the prep work, the crew will return tomorrow to continue prepping but also begin painting! We can’t wait to see the end results!

We are looking forward to working with and for you onsite and hope everyone has an amazing summer!


Danielle Baumgartner

Project Manager
Ph: 763-559-5296
Email

Angel Lopez

Production Manager
Ph: 952-208-0895
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423