RAIN DELAY: Friday, 6/28

Greetings and welcome to the blog for the upcoming project at Countryside West in Bloomington! We are thrilled to be working with and for you this year!

Building Projected Staining Start Date
Building 1 Tuesday, June 25th
Building 2 Thursday, June 27th
Buildings 3 & 4 Friday, June 28th
Buildings 5 & 6 Saturday, June 29th
Buildings 7 & 8 Monday, July 1st
Buildings 9 & 10 TBD
Buildings 11 & 12 TBD
Buildings 13 & 14 TBD
Buildings 15 & 16 TBD
Buildings 17 & 18 TBD
Buildings 19 & 20 TBD
Buildings 21 & 22 TBD
Buildings 23 & 24 TBD
Buildings 25 & 26 TBD
Buildings 27 & 28 TBD
Buildings 29 & 30 TBD
Buildings 31 & 32 TBD
Buildings 33 & 34 TBD
Building 35 TBD

Friday, June 28th: Good morning!

Unfortunately due to the rain the crew will not be staining today.  Fingers crossed for warm and sunny weather ahead!

Thursday, June 27th: Good afternoon!

After lots of rain the crew has finally been able to begin staining your decks! Today they are staining at Building #2.

The crew will be completing about 1 – 2 buildings per day for the staining.  If your deck is further down the schedule you can put your furniture back out on your deck if you would like while you wait for the crew to get to your building.  If you choose to do this we just ask that you follow along with the blog and bring your furniture back in a day before your building is scheduled to be stained.

Monday, June 24th: Good morning!

Our crew is onsite this morning working hard on Building 14. 

Building 14 decks are getting a fresh coat.

Rolling the paint on makes it easier to ensure all spaces get painted such as tall beams.

Thursday, June 20th: Good afternoon!

Due to projected bad weather, our crew is unable to be onsite and complete work today. We hope to be back onsite as soon as we can, weather permitting. 

Monday, June 17th: Good morning!

The crew is onsite and continuing to work their way around the route to pressure wash your decks.  Please make sure all furniture is removed from your deck for easy access.  Have a great start to your week!

Thursday, June 13th: Good afternoon!

The crew is continuing to work their way around to pressure wash.  They are currently washing Building 8.

Wednesday, June 12th: Good morning!

Your project is underway! Our crew is onsite this morning pressure washing the buildings in numerical order as seen in the map above. 

Thursday, June 6th: Greetings residents!

Welcome to the project blog for your upcoming project! This project blog will be used as a communication tool to relay pertinent project information regarding start dates, photos of progress, and updates to the finishing schedule.

Our crew is scheduled to be onsite Wednesday 6/12 to start pressure washing in numerical order (See map above). You may notice papers being posted with instructions on how to prepare for our crew to pressure wash your building. This paper also include details about the rest of your upcoming project. 

After allowing 4-6 days to dry our crew will be able to return onsite to start prepping and painting, this will most likely be on 6/17 weather permitting. 

Overall, this project should have minimal impact to your daily routine.  Please check back here to follow the progress of the project, updates to the daily schedule and for any weather delays.

Please reach out to the contacts below if you have any questions. Thank you and we are looking forward to getting started next week!


Tieler Travis

Project Manager
Ph: 763-559-5296
Email

Jason Schell

Production Manager
Ph: 651-503-2477
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423